Call us on : +91 7561 09 09 09

Queens Habitats Pvt.Ltd

iso 9001 universal Certification
Credai

News and Events

31-10-2018

First Sale of QUEENS COURTYARD

MR. C S SALEEM Founder Member of Credai Calicut and MR. BAIJU.M.NAIR Managing Director, Queens Habitats handed over the first sale agreement of our New project QUEENS COURTYARD to Dr. SREEKALA on behalf of Ms. Sreelatha.

31-10-2018

Launching of GOLD SERIES

Mr. Haseeb Ahammed Co-Founder Credai Calicut And Mr. Baiju.M.Nair Managing Director, Queens Habitats, Launching the New Gold Series Project QUEENS COURTYARD

10-03-2018

Queens Windsor Castle Apartment updates as on February 2018

1. External main painting works commenced. 2. Recreational area finishing works in progress. 3. Main Tiling work progressing in 12th and 13th floor (Work from top to Bottom ) 4. Aluminium window works progressing in 7th floor South eastern side ( work from top to bottom ) 5. Lobby putty work progressing in 5th floor (Work flow top to Bottom). 5. First

01-02-2018

Queens Windsor Castle Apartment updates as on January 2018

1. External Plastering completed. External Base coat painting nearing completion 2. Internal Electrical wiring and concealed plumbing work completed . 3. Bathroom tiling works completed. Main Tiling work progressing in 17 and 18 th floor (Work from top to Bottom ) 4. Aluminium window works progressing in 14 th floor South eastern side ( work from top t

01-01-2018

Queens Windsor Castle Apartment updates as on December 2017

1. External Plastering Nearing completion. External Putty work in progressing. 2. Internal Electrical wiring completed. Internal putty work nearing completion. 3. Bathroom tiling progressing in 17th and 18th 4. Plumbing works progrssing in 18 th floor. 5. Kitchen granite slab work completed in 17th floor 6. Balcony hand rail works completed. Staircase case handrail works eastern side completed. Western side in progress. As per the present schedule, the Plastering work of the project is expected to be completed by 20.1.2018.

12-12-2017

Queens Windsor Castle Apartment updates as on November 2017

1. External Plastering South East corner completed. North West Portion in Progress. 2. Lobby area Electrical and fire ducting works nearing completion. Air shaft Plastering work nearing completion. 3. Internal wiring and plastering completed. 17 th floor putty work in progress. 4. Fire Piping works 13 th floor in progress.

15-11-2017

Queens Windsor Castle Apartment updates as on October 2017

1. Roof top design pergola works completed. Dome work on the top in progress. 2. Laterite work whole building completed . External Plastering south west corner completed. South East in progress. . 3. Lobby area Electrical and fire ducting works nearing completion. Air shaft Plastering work nearing completion. 5. 14th floor putty work in progress.

01-10-2017

Queens Windsor Castle Apartment updates as on September 2017

1. Machine room and Water Tank works completed. Roof top design pergola works in progress. 2. External Plastering south west corner commenced. 3. Lobby area Electrical and fire ducting works in progress 5. 10 th floor putty work in progress. 6. 13 th floor internal plastering work in progress. 7. 18 th floor laterite work in progress.

25-08-2017

Queens Windsor Castle Apartment updates as on August 2017

1. 12th floor putty work in progress. 2. 14th floor internal plastering work in progress. 3. 18th floor laterite work in progress.

30-07-2017

Queens Windsor Castle Apartment updates as on July 30- 2017

Following Works have been completed 1. 18 th floor( Final Floor) roof slab completed. 2. Lift room and overhead Water Tank work in progress. 3. Lobby area Electrical and fire ducting works commenced. 4. Under ground water tank work completed. 5. 7th floor putty work in progress. 6. 10 th floor internal plastering work in progress. 7. 14th floor laterite wor

31-05-2017

Queens Windsor Castle Apartment updates as on May31st 2017

1. 16th floor roof slab completed. 17th floor southern side roof slab work in progress. 2. Eighth floor laterite work nearing completion. 3. Seventh floor plastering work nearing completion.

31-03-2017

Queens Windsor Castle Apartment updates as on March 31st 2017

Following works have been completed as of March 31 2017 13th &14th floor roof slab has been completed. Ninth floor roof plastering completed. Sixth floor laterite work completed.

31-01-2017

Queens Windsor Castle Apartment updates as on January 31st 2017

The following works have been completed in our project 'Queens Windsor Castle' at Paropadi, Calicut. 1. Ninth floor roof slab concrete completed. 2. Tenth floor column work in progress. 3. Seventh floor roof plastering in progress. 4. Fourth floor laterite work completed. 5. Fifth floor laterite work in progress.

10-01-2017

Windsor Castle Mockup flat in Calicut inaugurated

Mockup flat of Windsor Castle project in Paroppadi, Calicut has been completed and inaugurated. Please contact us to arrange for a live preview

31-12-2016

Queens Windsor Castle Calicut Flats December 2016 Updates

The following works have been completed in our project 'Queens Windsor Castle' at Paropadi, Calicut. 1. Eighth floor roof slab northern side completed. 2. Eighth floor roof slab southern side nearing completion. 3. Fifth floor ceiling plastering in progress. 4. Fourth Floor laterite work in progress.

30-11-2016

Queens Windsor Castle Flats November 2016 Updates

The following works have been completed in our project 'Queens Windsor Castle' at Paropadi, Calicut. 1. Seventh floor roof roof slab concrete completed. 2. Eighth floor column work in progress. 3. Fifth floor roof plastering in progress. 4. Fourth floor laterite work commenced.

15-06-2016

Queens Windsor Castle Update

The following work has been completed as on June 2016 1. Basement roof and wall plastering completed. 2. Second floor column work completed. 3. Second floor roof work in progress. We expect to complete second floor roof slab by 8.7.2016.

01-05-2016

Queens Windsor Castle Update

The following work has been completed at Windsor Castle 1. First Floor roof slab concrete completed 2. Ramp and staircases concrete completed 3.Sewage treatment plant concrete nearing completion

01-03-2016

Queens Windsor Castle Update

The following work has been completed in the project "WINDSOR CASTLE" at paropady,Calicut. 1. Work of Basement floor roof slab completed. 2. Work of ground floor northern side columns completed.

06-02-2016

Queens Windsor Castle Update

The following Basement work undertaken in last one month 1. Floor slab concrete completed. 2. Northern side walls concrete completed. 3. Southern side walls work in progress 4. Roof slab shuttering work in progress. The work of basement floor is expected to be completed by 20.2.2016

01-02-2016

Queens Grande Project Handover

Queens Grande Project Handover to Association in the presence of our chief guest Mr MT Vasudevan Nair.

30-12-2015

Windsor Castle Update

Work of basement floor is in progress .The completion is expected by 15th of Jan 2016

19-11-2015

Queens Windsor Castle

Piling , excavation for basement, pile chipping and pile cap has been completed

09-09-2015

Queens Windsor Castle Update

Basement floor excavation work has been completed and pile chipping is nearing completion. Pile cap work is in progress

20-08-2015

Queens Grande Update

We are glad to inform you that permanent KSEB connection has been obtained on 14-08-2015. Individual KSEB connections for flats are being processed.All common services for flats such as lift, common lobby lights, water lines, sanitation lines all are provisioned and functioning.CCTV work for surveillance of common area completed.Landscape work and Interlock pavement for driveway progressing.Entrance gate fixed, security room nearing completion.Fire and safety equipment installation completed.Generator for power backup installed and functioning.Swimming pool, Recreation area and Common lobby works progressing.First round inspection by Corporation of Calicut is completed and we constantly following up the process to obtain Occupancy Certificate.n

20-07-2015

Queens Windsor Castle Update

Piling work has been completed and excavation work for pile cap and basement flood has been commenced .

01-05-2015

Queens Grande Update

Following work has been updated in Queens Grande. Exterior Second coat work has been commenced and terrace tiling and basement concrete is completed.Ground floor lobby area work and fire and safety installation is nearing completion and rain water harvesting tanks have been completed

21-02-2015

ISO Certificate

ISO Certificate for Queens Habitats

22-01-2015

Queens Grande Update

Following work has been updated in Queens Grande. Common area false sealing has been commenced and tiling is nearing completion .Lift tile cladding has been completed and staircase tiling has been commenced .Bathroom fittings installation has commenced and compound wall work is nearing completion.

10-12-2014

Queens Grande updates

Queens Grande UpdatenFollowing work has been updated in Queens Grande. Exterior putty work is completed and painting has been commenced. Bed lift work is completed and 2nd lift is nearing completion. Common area fresh air duct work is in progress. Two overhead water tanks and lift room plastering completed and terrace water proofing is in progress. Inside doors installation commenced and individual apartments flooring 3rd to 11th floor is completed n

25-10-2014

Queens Grande Update

Following work has been updated in Queens Grande. Apartment exterior eastern side putty work completed. External compound wall work in progress.Fire stair case handrail work is completed and Common stair case handrail work nearing completion. STP tank work in progress. Swimming pool chemical and plastering work nearing completion.Third and fourth floor main tiling work in progress. Bathroom tiling work nearing completion. Bed lift work in progress

Queens Brochure

Download our brochure

Quick Contact

Tel: +91 495 4022440
Mobile: +91 7561 09 09 09
E-mail: sales@queenshabitats.com